Exclusive-Boeing supplier dispute has halted 777 freighter production for two months, sources say

By Thomson Reuters Oct 23, 2026 | 6:44 PM

By Dan Catchpole

SEATTLE, Oct 23 (Reuters) – Boeing’s dispute with a small Florida-based supplier has halted production of its 777 freighter for nearly two months and disrupted output of the 767, including freighters and KC-46 aerial refueling ​tankers, according to Boeing workers and court filings.

Boeing filed a complaint ‌in August alleging supplier Vaero had stopped delivering a critical wing component known as the trailing-edge rib kit, stalling work at the Everett, Washington, wing-production facility that supports the 777 freighter and 767 programs, according to a copy of the complaint reviewed by Reuters. The disruption was costing Boeing ‌as ​much as $6.5 million a day, the complaint said.

Boeing said ⁠in the complaint that the ⁠trailing-edge rib kit was an “indispensable” part and Vaero was the sole supplier.

Although the companies reached a settlement in late September, production of the 777 freighter has yet to resume, according to three Boeing workers familiar with the matter. They ​declined to be named because they were not authorized to speak publicly.

The dispute also disrupted production of the 767, a widebody cargo and military aircraft, the ⁠people said. Since the settlement, Boeing has received ⁠some parts for the 767 line, according to one of the ​workers.

The prolonged disruption highlights the fragility of aerospace supply chains, showing how a dispute ​involving a single supplier can halt production of aircraft that remain in ‌strong demand.

The lawsuit was first reported by Law.com in August, but the nearly two-month production disruption has not previously been reported.

Boeing declined to comment. Vaero did not respond to requests for comment.

BRINGING PRODUCTION IN-HOUSE

Boeing is trying to bring production of the trailing-edge ⁠rib kit in-house, according to two of the people. The component is used in wing assembly for the 767 and current-generation 777 freighter. Boeing’s 777X, which uses composite wings, ⁠has not been affected.

Without ‌the Vaero parts, Boeing removed two partially assembled 777 freighters ⁠from its final assembly line, according to one Boeing worker.

Using ​data from ‌aviation consultancy IBA, Reuters identified one of the aircraft ​as destined for ⁠FedEx.

FedEx did not respond to a request for comment.

Boeing has delivered 21 777 freighters so far this year, company data show. It also has a handful of freighters whose wings were assembled before the dispute and could still be delivered before year-end, according to two of the Boeing workers.

(Reporting by Dan Catchpole in Seattle; Editing by Joe ​Brock and Chris Reese)