Italy’s Lombardy to revise data centre law next week after application surge

By Thomson Reuters Oct 15, 2026 | 3:46 AM

By Giancarlo Navach

MILAN, Oct 15 (Reuters) – Just four months after approving legislation to regulate a surge in demand for data centres, Lombardy, Italy’s most populous region and home to Milan, is preparing ​to tighten the rules in response to growing public concern over ‌the pace and scale of new developments.

• Amendments to the law, approved in June, are due to be presented to the regional government on October 19 and could be approved by the regional council within about a month, regional councillor Massimo Sertori told ‌Reuters.

• “We ​will push to use as little agricultural land ⁠as possible and will seek ⁠to further discourage the use of farmland. Instead, projects should be developed on disused industrial sites, using innovative water-management systems to reduce water consumption,” Sertori said.

• The current legislation already gives priority to brownfield sites, ​including abandoned industrial areas, and strongly discourages projects on agricultural land or undeveloped greenfield sites.

• Under the existing rules, developments on agricultural land face ⁠construction charges that are 100% higher, while ⁠projects in parks or environmentally sensitive areas are subject to ​fees that are 200% higher.

• “We will also push to ensure that the energy ​used to power data centres comes from renewable sources,” Sertori ‌said.

• Since the law came into force, Lombardy has received more than 60 applications for data-centre projects, representing a combined proposed capacity of about 11 gigawatts (GW).

• Regional estimates indicate that 11 GW of data-centre capacity would consume about ⁠90 terawatt-hours (TWh) of electricity annually, compared with Lombardy’s current yearly electricity demand of around 65 TWh.

• By comparison, Italy is expected to add around 2.5-3 GW ⁠of new data-centre capacity ‌by 2030, with Lombardy accounting for between 1.5 GW ⁠and 2 GW over the next five years, according ​to the ‌latest industry estimates.

“It is clear that this is not ​sustainable. That ⁠is why the law needs to be revised,” Sertori said.

• Public opposition to data-centre developments has intensified in recent months.

• On October 3, residents in the town of Rho, near Milan, staged a protest against plans to build three data centres on a site covering about 3 square kilometres.

(Reporting by Giancarlo NavachEditing ​by Keith Weir)