FAA sees $100 million cost from tariffs on US air traffic control modernization plan

By Thomson Reuters Sep 17, 2026 | 12:45 PM

By David Shepardson

WASHINGTON, Sept 17 (Reuters) – The head of the U.S. Federal Aviation Administration said the agency expects about a $100 million cost from tariffs on the government’s more than $12.5 billion air ​traffic control modernization plan.

U.S. Representative Rick Larsen, a Washington Democrat who ‌is ranking member of the committee overseeing the FAA, told Reuters that FAA Administrator Bryan Bedford informed lawmakers the $100 million tariff cost was largely due to air traffic radar systems they are purchasing. Larsen criticized the tariffs for increasing the government’s costs.

“I’ve ‌asked ​them for specific amounts and what equipment is ⁠being impacted,” Larsen said. “I’m ⁠not a fan of tariffs. We’re trying to get the national aerospace system modernized and we’re going to pay tariffs because of the president’s policies.”

Congress approved $12.5 billion in funding last year to address the ​aging air traffic control system and boost controller hiring following decades of complaints about airport congestion and flight delays, as well as a ⁠series of technology issues in recent years. ⁠The FAA wants at least another $10 billion for phase ​two.

The cost of telecommunications upgrades has jumped from $4.75 billion to $5.91 billion, a government ​report said this week. Bedford said outdated telecom copper wires ‌should be replaced by September 2027.

Bedford also said two radar suppliers, RTX’s Collins Aerospace and Spain-based Indra Group, were moving radar production to U.S. facilities in Largo, Florida, and Kansas, respectively. He did not say where the production was moving from.

In ⁠January, the FAA awarded $780 million in contracts to RTX and Indra to replace up to 612 ground-based radars, most of which date back to the 1980s. ⁠Bedford said earlier ‌that many radars exceeded their intended service life and ⁠are increasingly expensive to maintain and difficult to support.

In ​March, ‌RTX said it was investing $26.5 million in its Largo ​facility to ⁠expand production, while Indra said it was investing $7.5 million in its radar facility in a Kansas City suburb to build next-generation air traffic surveillance radars.

Indra is also building next-generation digital radios for the FAA at the Kansas site under a separate $244 million contract.

(Reporting by David Shepardson; Editing by Chris Reese ​and Rod Nickel)